Q1-Which of the following is NOT a common column in a scrum Task board?
-Done
-Assigned to
-To do
-In Process
Q2– Which of the following might indicate a problem with progress in the sprint?
-Only high priority items shown in the “Done” column
-Too many tasks in the “In Progress” column after the sprint is well underway
-Low Priority items still in “To Do” near the beginning of the sprint
-All of these indicate problems
Q3– How much time does a Product Owner typically spend each week refining the backlog ?
-4 – 8 hours
-1 or 2
-40 hours — they are on the team full time!
-They only set priorities at the beginning of the sprint, not every week
Q4– What is the relationship between User Stories and Tasks in a scrum task board?
-Tasks are items that may
span multiple User Stories because they address some common feature
-Tasks are decomposed into User Stories that can be assigned to different team members
-User Stories are decomposed into tasks that can be assigned to different team members
-User Stories are assigned to individual team members but tasks are not
Q5– Which of the following is NOT a statement you would expect to hear from a scrum team member in a stand-up meeting?
-Priorities I set for myself are….
-Thing(s) holding me back from completing my work are….
-Yesterday I completed…
-Today I will work on….